Making the bid no bid decision
A ten-question scorecard for deciding which tenders and proposals to chase, and the BC-specific red flags that should push a job toward no.

Every estimate costs something: estimator hours, the owner's evenings, bid bonds, and the jobs you didn't price because you were busy pricing this one. Yet plenty of contractors bid almost everything that comes across the desk and then wonder why the win rate is low and the office is exhausted. A deliberate bid no bid decision, made the same way every time, is one of the cheapest growth tools a construction company has. This guide gives you a scorecard you can use this week, and explains the BC-specific traps that should push a job toward "no".
Why the bid no bid decision deserves a process
When the decision lives in one person's gut, three things happen. Good opportunities get passed over because the owner was on site that day. Bad ones get bid because "we need the work". And nobody can explain afterwards why the company chased what it chased. A short written screen fixes all three. It also makes the decision faster, which matters when a tender has a two-week window.
BDC's advice to construction companies is to focus on a niche and pursue the highest-potential opportunities rather than everything. A bid/no-bid screen is how that strategy shows up on a Tuesday afternoon when a new invitation lands.
A ten-question bid/no-bid scorecard
Score each question 0 (no), 1 (partly) or 2 (yes). Agree a threshold in advance, for example 14 out of 20, and a couple of questions that are automatic "no" if they score zero.
| # | Question | What a 2 looks like |
|---|---|---|
| 1 | Is this our type of work? | We've built several like it in the last few years |
| 2 | Is it a size we can carry? | Within the range we've delivered, without betting the company |
| 3 | Do we have the people on the dates shown? | PM and super named, crews available |
| 4 | Can our surety support it? | Bid and performance security confirmed with our surety |
| 5 | How will it be evaluated? | We know whether it's lowest price or scored, and we fit that |
| 6 | Do we know this owner or GC? | We've worked with them or have a warm introduction |
| 7 | Can we meet every mandatory requirement? | Every form, certificate and letter is in hand or easy to get |
| 8 | Is the risk allocation acceptable? | Standard contract form, no unusual supplementary conditions |
| 9 | Does it make money at a realistic price? | Margin holds at the price we think wins |
| 10 | Does it move us where we want to go? | It builds a reference, a relationship or a market we're targeting |
The scorecard is a tool for a conversation, not a calculator. If a job scores 13 but question 10 is a strong yes, you might bid it on purpose. If it scores 16 but you can't staff it, you don't.
BC-specific red flags that should push you toward "no"
A bid you can't stand behind
A bid bond isn't paperwork. The Surety Association of Canada explains that to provide a bid bond, the surety must consider you bondable from a performance perspective, and that if a contractor doesn't enter into the contract after posting a bid bond, it will be held responsible, corporately and usually personally, for reimbursing the bonding company. Put simply: if your surety can't support the job, it's a no-bid. If you're stretching to make the numbers work, that's a "no" before you've started. Our guide to surety bonds for contractors covers the details.
Mandatory requirements you can't meet in time
In a price-based solicitation, the Province says the award goes to the lowest compliant bidder, and all mandatory requirements and specifications must be met. In a provincial RFP, its guide says a proposal that misses even one mandatory cannot be considered. If a requirement needs something you don't have, such as a certificate, a named person or a site meeting you can't attend, decide early.
Paperwork that blocks the contract
For provincial contracts valued at $100,000 or more, the Province requires a tax verification letter before signing, and says that if a vendor can't produce one the Province will likely move on to the next qualified vendor. A WorkSafeBC account that isn't in good standing can cause similar problems with GCs. Fix these before you bid, not after you win.
Unusual contract terms
The BC Construction Association supports standard industry documents and opposes supplementary general conditions that alter or subvert their intent. When an invitation comes with pages of amendments to a standard form, price the risk honestly or walk away.
A job that only works if the scope is wrong
If the only way to win is to assume the drawings are complete when you know they aren't, you're not bidding a job, you're bidding a dispute.
Making the decision stick
- Decide within 48 hours of receiving the documents, before an estimator has sunk a week into takeoff.
- Write down the reason for every no-bid. Over a year, those notes show you which owners, sizes and contract forms you keep turning down, which is market intelligence.
- Tell the GC or owner politely. A clear "we'll pass on this one, please keep us in mind for the next" keeps you on the list. Silence can take you off it.
- Review wins and losses quarterly. Compare the scores of the jobs you won with the ones you lost. If you're losing everything below a certain score, raise the threshold. Debriefs, where available, feed straight into this.
How Pantheon helps
"Who to pursue, who to walk away from, and how to say it to the team" is how our service catalogue describes BD strategy, and bid strategy sits next to it under contract acquisition. We can help you set the scorecard, the thresholds and the review rhythm, then sit in on the decisions until the habit holds. If the deeper problem is too few opportunities worth bidding, the Business Development pillar is built for that. The first conversation is free and there's no obligation: get in touch or call 780-932-8977.
Frequently asked questions
What is a bid no bid decision?
It's a deliberate, repeatable decision on whether to pursue a tender or proposal, made early, using the same questions every time, before estimating hours are spent.
What should a bid/no-bid checklist include?
Fit, size, staffing on the dates shown, bonding support, how the job will be evaluated, your relationship with the owner or GC, mandatory requirements, contract risk, realistic margin and whether the job moves you where you want to go.
Should I bid on a job just to keep my name in front of a GC?
Not if you can't stand behind the price. A clear "we'll pass on this one, please keep us in mind for the next" keeps you on the list. Silence can take you off it.
When does bonding make a job a no-bid?
When your surety can't support it. The Surety Association of Canada explains that to provide a bid bond, the surety must consider you bondable from a performance perspective.